I've noticed the start datetime in the log appears to change to match the end datetime after the file has processed. Take the example image attached - the import highlighted had a start datetime of 27-03-2019 07:19:01 until the job completed, and then changed to 08:42:29 to match the end time when it finished.

Untitled-1.png
Accepted Answer Pending Moderation
Hello,
Yes, you are right. The first start time is when the import is actually getting prepared in CSVI Preview page. The start time gets updated again when the actual import starts and ends. I have fixed this time issue with the attached patch file. Can you load the patch file and check the start time again?
Attachments (1)
Kind regards,

Tharuna

=========================
If you use our extensions, please post a rating and a review at the Joomla! Extension Directory
  1. more than a month ago
  2. RO CSVI
  3. # 1
Accepted Answer Pending Moderation
Sorry, I've not had chance to test this yet. It'll try to make some time to look at it this afternoon.
  1. more than a month ago
  2. RO CSVI
  3. # 2
Accepted Answer Pending Moderation
I've not been able to process a big file yet to see it working in realtime, but I can confirm that the end and start times are now different in my Logs page.

Thanks!
  1. more than a month ago
  2. RO CSVI
  3. # 3
Accepted Answer Pending Moderation
Hello,
Thank you for confirming patch is working. We have also done little more improvements in start and end date and it will be included in our upcoming release along with date issue fixed with the patch.
Kind regards,

Tharuna

=========================
If you use our extensions, please post a rating and a review at the Joomla! Extension Directory
  1. more than a month ago
  2. RO CSVI
  3. # 4
  • Page :
  • 1


There are no replies made for this post yet.
Be one of the first to reply to this post!